[Davisgig] Fwd: Task Force Positive - City Staff Negative - Next Step for Community Broadband Needs your Help
Robert Nickerson
rob at omsoft.com
Fri May 31 18:36:14 PDT 2019
Hi All
This went out to the announce list just now. Please share far and wide.
I'll make a modification that is suitable for next door and fb and post
that next
Thanks
RAN
-------- Forwarded Message --------
Subject: Task Force Positive - City Staff Negative - Next Step for
Community Broadband Needs your Help
Date: Fri, 31 May 2019 18:32:16 -0700
From: help at dcn.org
Organization: DavisGIG Committee of DCN
To: davisgig-announce at list.davisgig.org
<davisgig-announce at list.davisgig.org>
Hi Davisites
We need your input at the next City Council meeting on Tuesday 6/4/19.
Last Wed was the final Broadband Advisory Task Force meeting. After
fulfilling its charge The BATF unanimously approved its final product, a
3 page letter, which unequivocally states a Fiber Based Community
Broadband network is feasible, should be further analyzed and pursued by
technical and financial professionals in coordination with city
engineering staff, and urges timely action.
This process went on 3 full years and was entering its 4^th . It
produced an excellent Feasibility Study Report, evaluated information,
talked to vendors, and generated and reviewed the results of a phone
survey and online poll in its final analysis.
Personally, I’m truly thankful these community leaders took their time
to evaluate and follow this process of evaluating feasibility to this
conclusion, and now it is time for DavisGIG to be more active again with
the Council to help move it onward.
In stark contrast, the staff report that the BATF letter is attached to
is very negative on cost alone due to the feasibility report we wrote
about last year.. Not a surprise for a report that states an $800 per
house marketing cost just to get the customer to join the community
fiber network.
The staff report draws on the very conservative Feasibility study report
which describes the costs of building the most expensive type of fiber
network, all at once, and with a business model of a traditional ISP
that competes against the Very Large ISPs. It also relies on the phone
survey about broadband we advised would be lackluster due to the fact
that no one does phone surveys any more. It really parrots points put
forward by the large incumbent carriers, to discourage municipal
broadband, and does not refer to any of the many economic development,
social justice, and pro competitive, smart city benefits a municipal
fiber investment would make. The staff report does not examine any
alternative designs, financing mechanisms or future needs which make
local control of Internet infrastructure desirable.
It completely ignores further analysis put forward by a subcommittee of
the BATF, as reported in a memo approved unanimously at the 3/27 meeting
that shows that the electronics are substantially cheaper, and a phased
installation approach allowing for project expansion based on revenues
from the initial phase. That memo advocates for the construction of the
core backbone ring and sub rings, that go throughout the entire city,
has substantial numbers of homes businesses and apartments passed, and
serves as an anchor ring that will generate immediate revenue and allow
the build out remaining neighborhoods.
It makes no mention of the network as a valuable asset that the City
would realize revenue from from citizens, business, and other companies
through leases. It makes no mention of working with community partners.
It ignores the fact that city and school buildings would have permanent
usable Internet connections for a one time cost. City Community and
Business Engagement staff, wants to end the effort and bring in big
fiber provider Grande/Wave/RCN, owned by private equity firm TPG Capital
to just carry on with the status quo, cherry picking neighborhoods and
giving away valuable city conduit for little return. This will setup
another monopoly control situation over physical Internet infrastructure
and fiber will be the last one installed, like Comcast’s control of
Coax, and ATT’s control of Copper.
So we need to put some effort into encouraging Council to do the right
thing here, which is follow the BATF letter and not the staff report.
Continue the effort of technical and financial analysis for a phased
build approach to a city-owned, community-operated open access fiber
ring or more.
This will be presented at the City Council on 6/4/19. Please provide
public comment via email or in person at the beginning of the meeting.
The BATF item is at the end of the evening, and I’d hate for you all to
be stuck at the meeting very late.
In support of that, we have generated a “talking points” type document
which refers to benefits identified by the Feasibility Study and
addresses concerns citizens identified in the DavisGIG broadband poll.
We hope you can use this to educate your neighbors and colleagues as to
why this will make everyone's quality of life better. As well, attached
is a sample letter you can use to send indicating your support for
community owned broadband and DavisGIG. Send it to
citycouncilmembers at cityofdavis.org
Thank you for your support
Davis GIG Committee of DCN
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.omsoft.com/pipermail/davisgig/attachments/20190531/170010bb/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Ring Design Principles.pdf
Type: application/pdf
Size: 114224 bytes
Desc: not available
URL: <http://list.omsoft.com/pipermail/davisgig/attachments/20190531/170010bb/attachment.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Template_CC060419.doc
Type: application/octet-stream
Size: 12800 bytes
Desc: not available
URL: <http://list.omsoft.com/pipermail/davisgig/attachments/20190531/170010bb/attachment.obj>